If you're buying a bottling line — beer, wine, honey, or a full automated setup — this is the checklist I actually use. It's built from managing roughly $180,000 in equipment spend over about 6 years. Maybe $195,000 if I add last year's spare parts budget, I'd have to check the system. Seven steps, in order. Each one has a checkpoint you can verify.

This is written for procurement managers, plant managers, or founders buying their first line. It is not for swapping a single filler head — that's a shorter job.

The 7 Steps

Step 1: Lock the Output and Product Spec Before You Get Quotes

The question everyone asks is "what does a bottling line cost?" The question they should ask is "what does this line need to produce on my worst day?"

Write this down on one page:

  • Bottles per hour (bph) — measured at your peak, plus 15–20% headroom
  • Bottle format — 330ml, 500ml, 750ml, honey jars, whatever you run
  • Product type — beer carbonation, wine temperature sensitivity, and honey viscosity at 12–15°C all behave differently in a filler
  • Capping and closure type — crown, screw, cork, corks with wire cage
  • Rinse, CIP, and gas flushing requirements

Checkpoint: If a supplier quotes without asking for this sheet, they're guessing. Move on.

Most buyers focus on the per-bottle cost and completely miss the factory floor, power, and utility footprint. That's the next step for a reason.

Step 2: Draw Your Floor Plan — Including Utilities

This is where projects die. A 12-head beer bottling line eats 30–45 m² minimum once you include the conveyor curves, accumulation table, and operator space. A honey bottling line needs heated tanks and longer transfer runs because the product doesn't flow like water.

Checkpoint: Before you sign anything, you should have measured or confirmed:

  • Available power (kW/A) at the breaker, not the wall plate
  • Water supply pressure and drain location
  • Steam or hot water availability if you're CIP-cleaning
  • Compressed air volume and quality (food-grade, oil-free)
  • Truck access for the delivery and rigging

I knew I should have had our electrician confirm panel capacity before paying the deposit, but thought "the spec sheet says 45 kW, we have 60." The panel was already loaded at 48. We spent an extra $4,200 on a subpanel and lost 3 weeks.

Step 3: Shortlist 4 to 6 Vendors — Not 12

A longer list sounds thorough. In practice, past six vendors, the technical comparisons blur and you stop doing real diligence.

Filter first, then quote:

  • Beer bottling line: the vendor must have at least one beer installation running comparable carbonation levels
  • Wine bottling line: ask about oxygen pickup (TPO) handling and filler vacuum stability
  • Honey bottling line: ask what happens to their filler when honey cools below 15°C. If they pause, that's your answer
  • Automated lines: ask who writes the PLC logic, and whether it's an open platform or locked to the vendor

Checkpoint: Request 2 references with installs dated within the last 18 months. Call them. Ask one question: "What would you have done differently?"

Step 4: Build the TCO, Not the Quote Comparison

This is the one most buyers skip. Equipment FOB price is maybe 55–65% of what you'll actually spend in year one. As of December 2025, based on quotes we collected for a mid-range 2,000 bph line, freight, rigging, install, and commissioning added 22–38% to the quoted price depending on vendor and origin.

Build a 5-year table with these rows:

  1. Equipment FOB
  2. Freight, insurance, customs duties
  3. Rigging and installation labor
  4. Commissioning and operator training
  5. First-year spare parts kit
  6. Utility upgrades (from Step 2)
  7. PLC/license fees (some vendors charge annually)
  8. Service contract or warranty terms

I built that spreadsheet after getting burned twice on hidden fees. The second time cost us more than the first. The cheaper line came in at $12,000 under the next quote — then billed $3,400 for the CIP automation interface, $1,800 for the nozzle spare kit, and $2,100 for a CE re-certification the vendor had implied was included. Net loss: roughly $28,000 once we count the 6-week delay.

To be fair, some vendors quote ex-works on purpose and expect buyers to handle logistics. That's not dishonesty. But you need to know which one you're talking to before you compare numbers.

Step 5: Nail Down Lead Time and Spare Parts Ownership

Lead times for bottling line equipment out of European and North American manufacturers typically run 14–22 weeks for a custom configuration (based on Q4 2025 quotes; verify current lead times directly, as they shift with component availability).

Ask these three questions in writing:

  • What's the guaranteed ship date, and what happens if you miss it?
  • Which spare parts are recommended for year one, and what's the cost?
  • Who stocks the critical wear parts — you, the vendor, or a local distributor?

Oh, and get the spares list in the contract, not in a separate PDF. We learned that the hard way when the "recommended kit" turned out to be a verbal description on a call.

Step 6: Confirm Compliance and Certification Documents

For equipment sold into the EU or imported to the US, you'll want:

  • CE marking with a Declaration of Conformity under Machinery Directive 2006/42/EC (verify current requirements at ec.europa.eu — the directive has been superseded by the Machinery Regulation 2023/1230, applicable from January 2027)
  • Food-contact compliance for product-touching surfaces — typically FDA 21 CFR 177 or EU 1935/2004 declarations
  • 3-A Sanitary Standards if you're processing dairy-adjacent or FDA-regulated products
  • Electrical standards — UL or equivalent for your jurisdiction

Checkpoint: Request the actual certificate, not a claim of compliance. Regulatory information changes; verify against the official regulator source for your market before purchase.

Step 7: Negotiate Payment Against Acceptance Milestones

Do not pay 100% on shipment. Use milestones, keep a meaningful retention, and define "acceptance" in writing.

A workable split for a standard line:

  • 30% deposit on order
  • 40% on factory acceptance test (FAT) at the vendor's site
  • 20% on site acceptance test (SAT) at your facility
  • 10% retention released after 30 days of running at stated output

Granted, this isn't always negotiable with larger manufacturers. But if it isn't, that's information.

Skipped the FAT on a small line once because we were rushing and "it's basically the same as last time." It wasn't. The capper head was misaligned and we spent the first two weeks on site chasing torque specs. Cost about $2,800 in downtime and rework.

Common Mistakes to Avoid

A few things that show up again and again in bottling line sourcing:

  • Comparing sticker prices across vendors with different scopes. Always rebuild the scope on your own terms before comparing.
  • Accepting "remote commissioning." For an automated line, on-site commissioning is the only version that catches mechanical alignment issues.
  • Skipping the FAT. It's the cheapest place to find problems.
  • Not asking who owns the PLC source code. If you ever want a second service provider, this matters a lot.
  • Buying the cheapest line. Budget vendors rarely match premium uptime — but there are exceptions. Check references before assuming either way.

The best part of finally getting our vendor process systematized: no more 2am worry sessions about whether the shipments will arrive on the day the production floor is cleared. There's something satisfying about a bottling line that just runs — after all the specs, spreadsheets, and site visits, seeing bottles come off the end at the stated rate is the payoff.

If you're sourcing a beer, wine, honey, or automated bottling line and don't want to run this process yourself, a turnkey sourcing partner can compress steps 3 through 7 — but only if you've done step 1 and step 2 first. No one can spec a line they can't see.

Pricing and lead time figures above are for general reference only, based on quotes collected from 2023–2025. Verify current pricing and delivery timelines with individual vendors before budgeting.