When this checklist applies

I've coordinated 40-plus rush bottling line projects over the last six years — beer, wine, honey, and a handful of juice and kombucha lines that weren't on the original plan. Three of those had a six-week window from purchase order to first bottle. This is the checklist I actually use when the call comes in at an inconvenient hour. Seven steps, run in order. The one people skip is step six, and it's usually the one that costs the most.

Use it when the line is down, when a launch date is already public, or when your current filler can't keep up with a contract you've already signed. Skip it if you have twelve months and nothing is on fire — you can afford to explore. Most of us can't.

Step 1 — Write the product spec before you email a single vendor

Every vendor will ask "what are you filling?" If your answer is "honey," you'll get ten different quotes for ten different machines. Raw honey at 20°C and pasteurized honey at 55°C are not the same product to a filler. Neither is wine at 12% ABV with visible tartrate crystals versus filtered wine.

In my first year, I made the classic rookie mistake: I assumed "standard" meant the same thing to every vendor. It cost me a $600 redo on a filler head — and that was the cheap version of the mistake. On a full line, "standard" can mean a changeover that wasn't budgeted.

Write the spec down. Viscosity (mPa·s) at fill temperature, solids content, pH, fill temperature range, whether you're filling still or carbonated, and the exact ABV or sugar range. Get this to one page. Then send it with every RFQ.

Checkpoint: Can a vendor size a pump and a filler head from your sheet without a follow-up call? If not, rewrite it.

Step 2 — Lock the container and closure format, not "approximately"

"500ml glass bottle" is not a specification. Put another way: a bottle is defined by its drawings, not its description. The neck finish is what the filler and capper actually interface with. A 38mm crown finish and a 29mm crown finish take different filler heads, different cappers, different changeover parts. If you order a beer bottling line and later switch to a 43mm lug cap for a specialty release, you've just bought a new capping station.

Send the container drawings — from the glass supplier, not from memory. Same for the closure. If you don't have drawings, get them before the PO, not after.

Checkpoint: Do you have a dimensioned drawing of the bottle, the closure, and the neck finish from the actual suppliers?

Step 3 — Size the line to peak, not average, and stop there

First-time buyers tend to size to average monthly demand. Then peak season hits, and they run eighteen-hour shifts on a line designed for one. I've watched a client do this with a beer bottling line during a summer contract — the line worked, but maintenance costs in year one ate the savings from buying a smaller machine.

Size to your 90th-percentile week, not your annual average. Personally, I size to the contract I've already signed, not the one I hope to sign. Then add 10% headroom. That's it. More than that and you're paying for capacity you can't fill.

This is where automation earns its premium, in my opinion. An automated bottling line doesn't just run faster — it removes the human pacing errors that show up at 2 a.m. on a Friday. Fewer manual changeovers means fewer mistakes at the exact moment you can least afford one.

Checkpoint: Does the quoted throughput match your 90th-percentile week plus 10%, at your product's real viscosity and container size?

Step 4 — Get the compliance matrix in writing before you compare quotes

If you're selling into the US, you're dealing with FDA 21 CFR Part 117 (current good manufacturing practice, in force since the FSMA preventive controls rule took effect in 2016–2018, depending on facility size). If you're selling into the EU, CE marking under Machinery Directive 2006/42/EC applies. If the product is dairy-adjacent or juice, 3-A Sanitary Standards will come up in the filler and valve design.

Ask each vendor for a written compliance matrix: standard, clause, how their equipment complies. Not a brochure. A document. If they can't produce one in a week, that tells you something about the post-sale support you're buying.

Per FDA 21 CFR Part 117 and EU Machinery Directive 2006/42/EC. Verify current applicability with your regulatory consultant and at fda.gov and eur-lex.europa.eu before signing — rules and interpretations change.

Checkpoint: Do you have a signed compliance matrix from each shortlisted vendor, covering your destination markets?

Step 5 — Decide new vs. used vs. rebuilt before you request pricing

I have mixed feelings about used equipment. On one hand, a used wine bottling line can save 40–60% versus new, and the mechanicals are often fine. On the other, spare parts availability is the risk nobody prices in. I've seen a buyer save $90,000 on a used line and then spend $14,000 in year two chasing a discontinued sensor.

The decision rule I use: if the machine has proprietary electronics or a discontinued PLC, treat it as rebuilt-with-a-warranty or pass. If it's mechanical — conveyors, uncramblers, rinsers, basic fillers — used is reasonable, provided you can see the maintenance log and the machine is available for inspection under power.

Even after I chose a particular used line last spring, I kept second-guessing. What if the rebuild wasn't as thorough as the dealer claimed? The three weeks until the FAT were stressful. It passed, but the lesson held: always include a factory acceptance test you can attend, in the contract, before final payment.

Checkpoint: Have you inspected the machine under power, and is the FAT a contractual milestone, not a courtesy?

Step 6 — Ask for the changeover matrix, not just the throughput number

This is the step most people skip, and it's the one that causes the most pain.

Throughput tells you how fast the line runs on one SKU. The changeover matrix tells you how long it takes to switch between SKUs — container size, closure, product, label. If you're a honey producer running three jar sizes and two product grades, changeover time is your real bottleneck, not fill speed.

A line that fills 200 bottles per minute but takes four hours to change over will lose to a line that fills 120 per minute and changes over in 30, if your run lengths are short. Do the math on your actual SKU count before you sign.

Checkpoint: Do you have a changeover matrix (minutes, by SKU pair) and have you multiplied it by your real production schedule?

Step 7 — Re-verify the utilities from the datasheet, not the sales deck

Every bottling line equipment quote lists utilities. Almost none of them match your plant. Steam pressure, compressed air quality (dew point and oil class matter for food contact), chilled water flow, electrical service, floor load, and drain capacity all get glossed over in the presentation and then become a change order after installation.

Glad I checked the compressed air spec last fall. Almost accepted the standard quote, which assumed a dry, oil-free supply we didn't have. The upgrade cost real money but saved the project. Miss that detail and the first thing your filler does is spray oil mist onto a food-contact surface during the FAT.

Print the datasheet. Walk your plant with a utility contractor. Mark what you have, what you need to add, and the lead time to add it. That lead time belongs in the schedule.

Checkpoint: Do you have a signed-off utilities sheet with lead times for anything you need to add, including compressed air treatment?

What goes wrong, and how to catch it early

Three failure points show up again and again.

Verbal lead times. Nobody quotes "eight weeks" on paper because eight weeks is rarely true. Ask for lead time in the written quote, with the start date defined (PO received vs. deposit cleared). They are not the same date, and the gap is where schedules die.

Utility specs from a PDF. Never accept utilities from a sales document. Get them from the engineering datasheet for the exact model you're buying. (Should mention: the datasheet often lists a range, and your plant needs to hit the worst-case end, not the best case.)

No FAT, or a FAT you don't attend. Factory acceptance testing is where you catch ninety percent of the defects that would otherwise blow up your install schedule. If the vendor is overseas and you can't attend, send a third-party inspector. The cost is small compared to a delayed install.

To be fair, most vendors I've worked with are honest and competent. The failures are usually communication failures, not bad actors. But the checklist exists because communication failures are expensive.

Run the seven steps in order. Don't compress them into a single week. The line will arrive when it arrives — what you control is whether it works on day one.